Facing brickssEptEm 5004

Technical data sheets

Color description
The bricks are through-coloured and the colour is black-blue.
Manufacturing dimensions (L x W x H)
ca. 220x72x52 mm (LxWxH)
Quantity / m² with a traditional joint
68 (12 mm)
Number / m² with a thin joint
77 (6 mm)

case studie sEptEm 5004

Powerful appearance thanks to dark facing bricks with contrasting finish

Powerful appearance thanks to dark facing bricks with contrasting finish

new library to become Zoersel's new village icon

The new library is set to become Zoersel's new village icon. The building is the result of a balancing exercise between designing a building that is tailored to the village on the one hand, and demonstrating its role as a public building on the other hand.

References

Search by city





Reference list sEptEm 5004
Postal code City Street Bond Joint Joint colour Window Roofing Remarks
9800 Astene Snoeckstraat Random bond 6 mm
8580 Avelgem Lindestraat 4 Random bond 6 mm
8800 Beveren Duivigestaat-Heidestraat Random bond 6 mm
5283 TZ Boxtel Zonnegoud 8 12 mm White
9660 Brakel Kasteelstraat Random bond 6 mm
8000 Brugge Velodroomstraat 71b Random bond 6 mm
9255 Buggenhout Kasteelstraat 128 Random bond 6 mm
9255 Buggenhout Kerkstraat 35 Random bond 6 mm
5087 TP Diessen Beerseweg 3C Random bond with strike-through joint 12 mm
9031 Drongen Treinstraat 26 Random bond 6 mm
Print all

How to Install ?

Preparation of the construction site

Quality brickwork starts with the proper storage of the materials. Provide a firm level base so that bricks are not in contact with rain and/or dirt.  
As clay is a natural material, successive production runs of the same kind of bricks may present colour variations and size tolerances.
The following precautions will help minimizing this:
  • Always order the full amount of bricks required for a specific site. In this way, the entire order can be made during one production run.
  • Try to have the full order supplied at one time. If this creates several deliveries, always mix a number of packs from the previous delivery with a number of packs from the new delivery. This procedure is especially recommended in case of re-order or for an additional order.
  • Take bricks diagonally across the pack.
  • Draw and use bricks from at least five different packs.
  • For setting out, use bricks from the delivery made to the site in question. Do not exclusively use the theoretical dimensions of the brick, or samples previously supplied, or different production run from that intended for the site.
  • As soon as the bricks arrive on site, check delivery tickets and certificates against the specification and order. Also check that there are no visible inconsistencies with the order.
  • Do not lay bricks in freezing weather or protect the ‘fresh’ masonry with insulating mats in order to avoid frost damage to the mortar.
  • In the case of prolonged dry hot weather, lightly dampen the newly laid brickwork to stop the mortar drying and curing too quickly.
  • Do not lay bricks in precipitation in order to prevent mortar from running on the wall.

Avoid Efflorescence

Brickwork is sometimes marred by white bloom. This efflorescence is usually caused because bricklaying is done under unfavourable weather conditions. The necessary protective measures are often not implemented due to a tight schedule and fast building pace. In very wet conditions, water in soluble substances can result in efflorescence on the surface. In spring as well as autumn, after a wet period (when the brickwork has dried again), soluble substances can rise to the surface as a result of moisture transport. After evaporation of the water, a white bloom is left behind. (Source: Efflorescence on brickwork – Heidelberg Cement Group)
 
Efflorescence on brickwork is always likely to occur. There is no brick - or combination of a certain brick with a specific mortar - that is absolutely efflorescence-free. By taking a few simple precautions, the risk of efflorescence can be reduced.
  • During and after laying, protect the newly built brickwork for a height of at least 60 cm - but ensure there is airspace between the brick face and the waterproof covering.
  • Provisionally install rainwater down pipes to avoid saturation of the newly laid brickwork
  • Never lay bricks in driving rain conditions